Source - DSO Service Acquisition Interaction Comillas (2024)
Academic journal article analysing the three mechanisms DSOs use to acquire flexibility — network tariffs, flexible connection agreements (FCAs), and local markets (LFMs) — defining design dimensions for each and performing pairwise interaction analyses to identify synergies, conflicts, and context-dependent interactions. Part of the BeFlexible Horizon project.
Bibliographic details
- Title: “Unlocking flexibility from third-party resources: decoding the interaction between mechanisms for acquiring distribution system operator services”
- Authors: Ormeño-Mejía, J.; Chaves-Ávila, J.P.; Troncia, M.
- Institution: IIT — Instituto de Investigación Tecnológica, ICAI School of Engineering, Comillas Pontifical University (Madrid)
- Journal: Current Sustainable/Renewable Energy Reports
- DOI: 10.1007/s40518-024-00236-7
- Year: 2024 (published online)
- Funding: BeFlexible project (EU Horizon, grant no. 101075438)
- Raw file:
raw/paper-rev01-extracted.txt
Summary
Provides the most rigorous treatment available of the multi-mechanism nature of DSO service acquisition. Defines each mechanism via structured design dimensions (10 per mechanism across four meta-dimensions: locational, temporal, product, and assets), then performs pairwise qualitative interaction analyses for all three mechanism pairs. Each cross-option is rated:
- Green: no loss of economic efficiency from simultaneous use
- Orange: potential loss of efficiency; requires contextual analysis
- Red: misalignment or infeasibility; simultaneous use causes definite efficiency loss
- Grey: irrelevant / not applicable
Core argument: the three mechanisms are designed as if the others don’t exist, but coexist in practice — creating double-signaling, double-charging/rewarding, and market power distortions. Co-design is the policy recommendation.
Design dimensions taxonomy (abbreviated)
Network tariffs
Four meta-dimensions: Locational (system-wide / zonal / nodal granularity), Temporal (yearly / seasonal / daily blocks / hourly charges; static vs dynamic vs ex-post price-setting; measurement granularity), Charges (cost allocation method; charging variable: used/contracted/physical capacity or energy; customer differentiation; symmetry of offtake and injection charges), Assets (technology-agnostic or technology-specific).
Flexible connection agreements
Six key dimensions: Duration (temporary / permanent), Connection costs (deep / shallow / avoid or defer reinforcement), Activation trigger (emergency / maintenance / congestion / peak off-peak / seasonality), Principle of access (pro-rata / LIFO / auction / congestion-created level), Compensation payments (fixed / set by LFM / LFM-indexed / none), Maximum curtailment (capacity / energy / monetary limitation), Eligible customers (generation / demand / storage).
Local markets for DSO services
Ten dimensions: Flexibility need grid level (HV / MV / LV), Negotiation timeframe (long / short), Contract length (yearly to hourly), Temporal bid granularity (>1h / 1h / 30 min / 15 min), Response time (>1h / 30–60 min / 15–30 min / <15 min), Transactional object (capacity availability / energy activation), Power type (active / reactive), Direction (upward / downward), Symmetry (symmetric / asymmetric products), Source (generation / demand / storage).
Key interaction findings
Network tariffs ↔ Local markets
Green (compatible):
- LFM fills gaps where tariffs lack locational granularity (system-wide tariff + zonal/nodal LFM)
- LFM fills gaps where tariff temporal granularity is coarse (yearly tariff + hourly LFM)
- LFM can address reactive power needs that tariffs cannot signal
Orange (context-dependent):
- When both have granularity for the same period and area — double-signaling risk; customer is rewarded twice for same service
- When LFM temporal bid granularity is longer than tariff charge granularity — averaging effects create inefficient price signals
- Ex-post tariff pricing + day-ahead LFM requires careful design to avoid double compensation
Red (incompatible):
- Measurement granularity mismatch: if tariff meter reads at “daily blocks” but LFM requires hourly bids, technical infeasibility results
Network tariffs ↔ Flexible connection agreements
Green:
- Flat-rate tariffs coexist with most FCA designs without conflict
- When FCAs have no compensation payments, interaction with tariffs is generally conflict-free
- Connection agreements address reactive power / voltage constraints that tariffs cannot
Orange:
- Shallow connection cost recovery + socialized network tariff risks double-charging
- Congestion-triggered curtailment activation with tariff congestion signals risks double-rewarding
- Nodal tariff pricing + compensation payments in FCAs requires detailed conflict analysis
Flexible connection agreements ↔ Local markets
This pair has the most conflicts:
Red (definite infeasibility):
- Ex-post curtailment notification blocks LFM participation entirely — if customers don’t know about curtailment until after the fact, they cannot bid into day-ahead markets
- Emergency activation (no advance notice) makes combined operation infeasible; customers cannot adapt LFM bids to emergency curtailment orders
- LIFO access principle creates queue uncertainty that undermines reliable LFM bidding
Orange:
- Intra-day curtailment notification overlapping with real-time LFM — double-rewarding risk if both activate simultaneously
- Temporary FCAs with shorter duration than LFM contract length → unfeasible combination when FCA expires during contract period
- Congestion-triggered activation + seasonal pre-definition of curtailment + yearly LFM contract length → timeline misalignments
Green:
- Permanent FCAs (known timeline) coexist well with LFMs — customers can plan LFM participation around known curtailment windows
- No compensation payments in FCA → LFM interaction generally clean
- Same-type eligible customers in FCA and source/direction in LFM → compatible
General conclusion
When mechanisms send the same economic signal twice, customers face double charging or double rewarding, distorting efficient behaviour. Novel co-design practices are required to exploit combined efficiency. Orange cases require quantitative context-specific analysis — identified as future research.
Relevance to wiki
Directly enriches:
- Flexibility Market — mechanism co-design principle; three-way interaction map; FCA–LFM green/orange/red framework
- Flexible Connection Agreements — design dimensions for FCAs as a distinct concept page (new)
- Villkorade Avtal — Swedish villkorade avtal is the national implementation of FCAs; design dimensions apply
- Network Code on Demand Response — NC DR Art. 31 coordinates FCAs with LFMs; this paper’s interaction analysis applies directly to NC DR T&C design
- Congestion Management — three mechanisms as the DSO congestion toolkit; their co-design requirements
- Distribution System Operator — DSOs deploying all three simultaneously; co-design as regulatory challenge
Key Sweden observation: Sweden will face the FCA–LFM interaction issue acutely. Villkorade avtal use congestion-triggered activation (red cross-option with ex-post notification) and day-ahead LFMs coexist at the same DSOs — the paper’s findings are directly prescriptive for NC DR T&C design.
Data gaps
- Quantitative case studies validating orange/red classifications with actual market data — paper identifies this as future research
- Swedish-specific analysis: which cross-options apply in the villkorade avtal + SWITCH / Effekthandel Väst context?