Source - Ei Flexibility in Distribution Grids (2023)
Full title: Flexibilitet i distributionsnäten — Förutsättningar för ett effektivt nätutnyttjande (Flexibility in Distribution Grids — Conditions for Efficient Grid Utilization)
Published: April 2023 by Ei (Energimarknadsinspektionen)
Authors: Filip Hellberg, Jennie Nyberg, Fredrik Prinz Blix, Jenny Radkova, Linda Schumacher, Marie Swenman
Context: Sub-assignment 3 of a government mandate (August 2022) given to Ei, Svenska kraftnät, Energimyndigheten, and Swedac to develop conditions for realizing flexibility potential in the electricity system. Focus: promoting flexibility at local/distribution level where it is socio-economically efficient.
Key content
DSO flexibility tools (Chapter 3)
Ei identifies three categories of DSO flexibility tools:
-
Network tariffs (nättariffer) — cost-reflective tariffs that give customers price signals to adjust usage. New Ei regulations (EIFS 2022:1) require time-differentiated capacity tariffs by January 2027. Localization signals (different tariffs by grid area) discussed but not yet implemented.
-
Market-based procurement — purchasing flexibility services on a market or through competitive procurement. Art. 32 of the Electricity Market Directive requires this. DSOs must submit product specifications to Ei for approval — as of 2023, none had done so.
-
Non-market-based methods — primarily Villkorade Avtal (conditional connection agreements). Ei classifies these as non-market-based redispatching under Art. 13 of the Electricity Market Regulation.
CAPEX bias in revenue cap regulation (Section 3.2, 6.2)
A critical finding: the Swedish intäktsramsreglering (revenue cap regulation) creates a CAPEX bias — DSOs have economic incentives to invest in grid expansion rather than procure flexibility services, even when flexibility would be more cost-effective:
- Capital investments earn regulated return on the capital base (kapitalbasen)
- Flexibility procurement is classified as operating expenditure (löpande påverkbara kostnader) subject to efficiency requirements
- OPEX based on historical reference period with lag; CAPEX included from year of commissioning
- Ei acknowledges this bias and is working on methodology reform
Swedish flexibility market pilots (Chapter 4)
Three pilots evaluated:
| Pilot | Initiators | Geography | Platform | Period |
|---|---|---|---|---|
| CoordiNet | Vattenfall Eldistribution, E.ON Energidistribution, Svk | Uppsala, Skåne, Gotland, Jämtland/Västernorrland | SWITCH (by E.ON) | 2019–2022 |
| sthlmflex | Ellevio, Vattenfall Eldistribution | Stockholm region | NODES | 2020– |
| Effekthandel Väst | Göteborg Energi, Mölndal Energi | Gothenburg | NODES | 2022– |
Key findings:
- Primary driver: regional DSOs managing peak demand against their subscription to Svenska kraftnät’s transmission grid (abonnemang mot överliggande nät)
- Limited economic savings so far, but pilots enabled new customer connections and built crucial operational knowledge
- Thin market problem (sällanköpsmarknad): congestion events are infrequent and geographically limited → low liquidity, few activations, weak revenue for providers
- Supply: primarily flexibility from large heating plants (värmeanläggningar); in Uppsala and Stockholm, supply was generally sufficient when needed
- Skåne: demand exceeded supply — no new connections directly enabled
- Pricing: pay-as-bid (budprissättning) used; marginal pricing initially tested on CoordiNet but abandoned as technically challenging
- Products: primarily energy-only (“fria bud”); some availability products tested (tillgänglighetsprodukter)
- Minimum bid: sthlmflex lowered to 0.1 MW to increase participation
- Cascade model: bids not cleared locally forwarded to Svk’s mFRR market — tested on CoordiNet and sthlmflex
Barriers identified (Section 4.3–4.4)
- Low revenue and rare activation — flexibility providers called too infrequently and paid too little
- Svk temporary subscriptions as price cap — DSOs can request temporary subscription increases from Svk, which are sometimes cheaper than market flexibility, suppressing willingness to pay
- Insufficient transparency — providers lack information on DSO needs and willingness to pay
- Multi-market participation — providers want to participate across local, FCR, and mFRR markets but face technical and coordination barriers
- Lack of standardization — different communication formats, qualification processes, and products across markets
- Data access inequality — suppliers/aggregators have unequal access to customer metering data; solved by elmarknadshubb
- Regulatory uncertainty — upcoming EU rules (NC DR) creating wait-and-see behavior
- Knowledge gap — potential providers don’t know how to participate
Upcoming EU rules (Chapter 5)
Analysis of ACER Framework Guideline (December 2022) and expected NC DR content:
- Three sets of national terms to be developed jointly by DSOs and TSOs: (1) service provider conditions, (2) local market design, (3) inter-operator coordination
- Product qualification to use ex-post verification (product verification) as default for local services
- Baseline methodology requirements
- Transparency and information obligations
Market design analysis (Chapter 7)
Ei favors nationally integrated market design:
- Either DSOs trading on a common platform, or integration with existing markets (intraday, mFRR) using geographically tagged bids
- GOPACS (Netherlands) cited as example of using existing intraday platform for DSO congestion
- Availability products: Ei prefers energy-only to avoid resource lock-in, but acknowledges DSO need for delivery certainty
- Market power risk: geographic limitation of local markets creates risk of local market power and strategic bidding (inc-dec gaming)
- Pricing method: marginal pricing better for long-term investment signals; pay-as-bid used in practice due to simplicity
- Market operator: DSOs can currently operate platforms as network business, but law (ellagen 3 kap. §12) generally prohibits DSOs from non-network activities
Recommendations (Chapter 8)
- Resume elmarknadshubb — central electricity market hub (like Norway’s Elhub) for equal access to metering data. Paused since 2020 due to missing legislation.
- Establish Ei innovation center — regulatory guidance platform; possible stepping stone to regulatory sandboxes
- No new national rules — defer to upcoming EU regulation (NC DR)
- Continue improving: revenue cap incentives, tariff design, DSO-TSO coordination
Significance for the wiki
This source:
- Fills the “Swedish flexibility landscape: pilots, platforms, volumes” data gap flagged on Flexibility and Flexibility Market
- Provides Ei’s own assessment of the CAPEX bias problem — a structural barrier to flexibility procurement
- Documents the three major Swedish flexibility market pilots with concrete operational details
- Confirms the elmarknadshubb as critical missing infrastructure
- Aligns with and anticipates the Network Code on Demand Response framework