Source - Vattenfall Eldistribution Nätutvecklingsplan 2025-2034
Source metadata
| Field | Value |
|---|---|
| Title | Nätutvecklingsplan 2025–2034 |
| Author | Vattenfall Eldistribution AB |
| Confidentiality | C1 Public |
| Pages | 48 |
| Type | DNDP (mandatory biennial publication per EIFS 2024:1) |
| Raw file | vattenfall-eldistributions-natutvecklingsplan-2025-2034.pdf |
Summary
Vattenfall Eldistribution‘s first mandatory DNDP (nätutvecklingsplan), published December 2024, covering 2025–2034. Covers grid overview, capacity forecasts, planned investments (22 major projects), flexibility service needs, and adequacy assessment — plus a Chapter 5 responding to consultation feedback. Bilaga 1 (municipality-level local grid forecasts) is a separate document (Source - VF NUP Bilaga 1 Prognos Lokalnät per Kommun).
Key claims
Grid overview
Vattenfall divides its network into five areas: Norr, Mellan, Stockholm, Öst, Väst. This coarser-than-county division was deliberate — justified by NDA agreements with large industrial customers and by the fact that regional grid constraints span multiple municipalities. The choice was contested in consultation (see FAQ below).
- Total current load: approximately 11,000 MW
- Expected growth 2025–2034: +7,500 MW consumption (of which ~3,800 MW in Norr), +4,500 MW production
- Local grid: characterized as “stable” for the period — moderate growth manageable with planned investments in most areas
- Pipeline not in the forecast: 18,000 MW consumption applications + 38,000 MW production applications excluded due to low maturity or stamnät capacity block
Forecast methodology
- Only includes customers who have signed a förstudieavtal (pre-study agreement) — the maturity threshold is high
- Local grid: annual collection of municipal exploitation plans from ~90 municipalities; sannolikhetsjustering (probability-adjusted) by planning stage
- Regional grid: bottom-up from customer project maturity; production forecast based on live connection applications only (no top-down production scenarios — a limitation acknowledged)
- Price-driven demand reduction NOT modelled — Vattenfall acknowledges this creates a systematic upward bias
- Prognosen describes maximum possible demand, not expected demand profile; no hourly resolution yet (under development)
Demand drivers per area
- Norr: steel industry electrification (Gällivare), car-testing industry (Arvidsjaur/Arjeplog), wind/solar
- Mellan: solar build-out throughout, NordSyd restructuring, industrial servers/data centers
- Stockholm: residential/commercial growth, EV charging, 70→130 kV grid rebuild
- Öst: industrial electrification (Sörmland), Gotland demand growth, wind/solar
- Väst: petrochem electrification (Stenungsund), auto industry (Göteborg area, Projekt Ture), solar
Flexibility stance — no market-based procurement
The most significant finding: Vattenfall explicitly states it sees no conditions for market-based flexibility services at any of its constrained locations. The stated reason:
“Vattenfall Eldistribution AB:s bedömning är att det i dagsläget inte finns förutsättningar för marknadsbaserade flexibilitetstjänster på dessa platser, varför bilaterala avtal med de enskilda verksamheterna övervägs.”
Vattenfall’s threshold for a viable flexibility market:
- Supply ≥ 5× demand
- ≥ 5 independent actors
- No single actor providing >50% of supply
Their conclusion: these conditions are not met anywhere in their network.
DNDP Section 3.3.1: “Med utgångspunkt i nuvarande prognoser ser Vattenfall Eldistribution AB i dagsläget inget behov av andra flexibilitetslösningar än villkorade avtal med kund.” (With current forecasts, Vattenfall sees no need for flexibility solutions other than villkorade avtal with customers.)
This directly explains why Vattenfall reported N/A for all flexibility service needs in Ei’s DNDP data tool — a deliberate policy choice, not a reporting gap.
Flex market pilot closures
Vattenfall has closed both of its flexibility market pilot projects:
- Uppsala pilot (UppFlex, CoordiNet-era): “Med nya förutsättningar har Vattenfall Eldistribution beslutat att avveckla detta pilotprojekt”
- Stockholm pilot (sthlmflex participant): same language — “Med nya förutsättningar har Vattenfall Eldistribution beslutat att avveckla detta pilotprojekt”
The “new conditions” (nya förutsättningar) are not further specified but context points to stamnät constraints in Stockholm (Vattenfall was managing subscriptions against the overlying grid, not local congestion) and insufficient liquidity in Uppsala.
Vattenfall does use Villkorade Avtal in both Mellan (Uppsala area local grid) and Stockholm local grid. The flex market pilots were addressing regionnät constraints against Svk subscriptions — a different problem from local grid congestion.
Cost comparison: flex vs grid
Section 3.1.2 contains Vattenfall’s explicit cost comparison, based on their approved methodology for villkorade avtal:
| Solution | Cost |
|---|---|
| Grid investment (capital + other costs) | 0.27 MSEK/MW/year |
| Flexibility availability contract | 4–8 MSEK/MW/year |
Vattenfall notes this is a theoretical calculation and acknowledges that few actors currently meet the technical requirements for grid-replacing flexibility services. The ratio (≈15–30×) is their primary argument against market-based flex as a grid substitute.
Compare with FlexAbility’s quantified DSO value cases from Ellevio’s network (utnyttjandegrad, abonnemangsoptimering: 10,000–122,000 SEK/MWh) — a different framing of the same question. The Vattenfall calculation addresses capital cost per MW, not marginal value per activation.
Investment programme — 22 major regional grid projects
| No. | Area | Project | Status | Commissioning |
|---|---|---|---|---|
| 1 | Norr | Grundfors | Inväntar tillstånd | 2026–2028 |
| 2 | Norr | Blaiken–Sandselehöjderna (wind, Sorsele) | Inväntar tillstånd | 2026–2027 |
| 3 | Norr | Elintensiv verksamhet Gällivare | Inväntar tillstånd | 2029 |
| 4 | Norr | Regionnätsförstärkning Luleå | Påbörjad | 2025–2029 |
| 5 | Norr | Strukturförändring Nedre Skellefteå Älvdal | Påbörjad | 2024–2027 |
| 6 | Norr | Strukturförändring Vargfors-Arjeplog | Påbörjad | 2026–2029 |
| 7 | Norr | Elintensiv verksamhet Boden | Påbörjad | 2025 |
| 8 | Norr | Tuggen | Tillstånd beviljat | 2026 |
| 9 | Mellan | Huvudprojekt Sala (70→130 kV) | Tillstånd beviljat | 2026–2029 |
| 10 | Mellan | Elintensiv verksamhet Gävleborg | Påbörjad | 2025–2029 |
| 11 | Mellan | Kapacitet Västmanland (NordSyd Västeråsbenet) | Tillstånd beviljat | 2025–2030 |
| 12 | Mellan | Himmeta–Arboga–Kungsör | Tillstånd beviljat | — |
| 13 | Mellan | Huvudprojekt Enköping | — | — |
| 14 | Mellan | Husbyborg–Litslena (20→40 kV) | — | — |
| 15 | Stockholm | Kapacitet Stockholm (~100 sub-projects, 20 mil 70→130 kV) | Ongoing | 2023–2034 |
| 16 | Öst | Gotland (new transformer for Svk 220 kV connection) | Planerad | 2028 |
| 17 | Öst | Elintensiv verksamhet Sörmland | Pågår | 2025–2029 |
| 18 | Öst | 130 kV-ledningar Sörmland (Flen–Nyköping, ~5 mil) | Planerad | 2027–2029 |
| 19 | Öst | Elintensiv verksamhet Oxelösund (2×74 km 130 kV + 400 kV) | Pågår | 2025–2026 |
| 20 | Väst | Ture (Göteborgsregionen, industrial electrification) | Pågår | 2025–2031 |
| 21 | Väst | Stella | Planerad | 2028 |
| 22 | Väst | Stamnätstation Stenungsund | Planerad | 2029–2030 |
90% of Vattenfall’s growth investments are covered by these reported projects; 75% of total investments are for other purposes (renewal, safety) not captured in the DNDP.
Adequacy assessment (Ch. 4)
| Area | Own network | Overlying stamnät |
|---|---|---|
| Norr (normal growth) | Meets need | Largely OK |
| Norr (large industry) | Villkorade avtal needed — Svk subscription not granted | Constrained |
| Mellan | Meets need (with NordSyd Västeråsbenet from 2028) | Roslagen timeline unknown |
| Stockholm | Meets need (regionnät rebuild 2023–2034) | Improving from H2 2024 |
| Öst | Meets need | OK |
| Väst | Villkorade avtal for industry + production | Stamnät capacity not yet granted |
Key qualifiers: Vattenfall explicitly excludes from this assessment all applications blocked by Svk capacity — the plan only covers what can actually be connected given current stamnät subscriptions.
Consultation FAQ responses (Ch. 5)
Seven recurring consultation issues addressed:
- Coarse geographic resolution — justified by NDA obligations and grid structure; bilaga 1 added as compromise
- No capacity map — Vattenfall declines; notes EU requirements coming (likely before 2026/27 DSO publication deadline); describes capacity in terms of ability, not MW figures
- Only mature-project customers in forecast — deliberate; immature projects too uncertain; separately discloses excluded volumes
- Customers blocked by Svk capacity — excluded from forecast; Vattenfall actively lobbies Svk for capacity grants
- Transparency on queue position — customer-specific confidential; fair queue principles described
- Anticipatory investment based on municipal plans — constrained by need for välgrundade antaganden (well-founded assumptions) per licensing requirements
- Apparent dismissal of flex — extensive FAQ response clarifying that flex is not rejected, but conditions for market-based flex not yet met; villkorade avtal are the current operative tool; flex development work ongoing
Relevance to wiki
Resolves existing data gaps
- Distribution Network Development Plan: “DNDPs from Vattenfall Eldistribution and Ellevio” — Vattenfall now resolved
- Flexibility Market: Vattenfall closed both pilots — now explained and sourced
- SWITCH: UppFlex (Vattenfall/Uppsala CoordiNet extension) closure — now confirmed
Contradicts / updates existing wiki
- Flexibility Need Assessment: Vattenfall’s N/A in Ei’s data tool is now explained
- Villkorade Avtal: Vattenfall’s use of villkorade avtal in both Mellan (Uppsala local) and Stockholm local grid — adds detail
New concepts / entities
- Vattenfall’s 5-area structure (Norr, Mellan, Stockholm, Öst, Väst) — new granularity
- Vattenfall’s explicit flex market liquidity threshold (5×, 5+ actors) — first DSO to quantify this
- 0.27 MSEK/MW/year grid cost benchmark — adds to Congestion Management value cases
- Projekt Ture (Göteborg industrial, 2025–2031) — new major project
- Kapacitet Stockholm (~100 sub-projects, 70→130 kV, 2023–2034) — major investment programme