NordSyd
Not a single project but four separate branches (Uppsala, Västerås, Karlstad, Hallsberg) at different stages — some already in contracting, Hallsberg still just under consideration — and Svk's own 2050 modelling finds the economic payoff shifting between them over time, with Snitt 1 reinforcement growing more valuable as northern demand surges while further Snitt 2 work becomes less valuable precisely because NordSyd already added capacity there.
Building the fix temporarily makes the local problem worse — E.ON's own network plan states that during 2027-2030, NordSyd construction itself will more heavily load its Gävleborg and Västernorrland regional grids as power reroutes through alternative paths, cutting capacity for new connections in those counties until the project completes.
NordSyd (North-South) is Svenska kraftnät‘s flagship transmission grid initiative to increase electricity transfer capacity from northern to southern Sweden. It addresses the fundamental Bidding Areas imbalance: surplus generation in SE1–SE2 and deficit consumption in SE3–SE4.
Four branches
The initiative consists of four parallel reinforcement routes through central Sweden:
| Branch | Route | Key projects | Status |
|---|---|---|---|
| Uppsala | Mehedeby → Jälla → Plenninge → Odensala | New double 400 kV lines, new substations at Jälla and Plenninge | Preparation/contracting phase |
| Västerås | Horndal → Munga → Hamra | New 400 kV substations and lines through Västmanland | Preparation phase |
| Karlstad | Borgvik → Malsjö | New 400 kV line through Värmland | Preparation phase |
| Hallsberg | Storfinnforsen → Bäsna → Hallsberg | New double 400 kV inland lines, the longest route | Under consideration |
Additionally, the Midskog–Malsjö double 400 kV line project (planned 2035) is part of the northern NordSyd corridor, connecting into the Karlstad branch.
Capacity targets
Svk’s Planering för ökad elanvändning (February 2025) sets explicit capacity targets for the two main internal snitts:
- Snitt 1 (SE1–SE2): target 7,500 MW by 2045 — up from 3,300 MW today (+4,200 MW)
- Snitt 4 norrgående (SE3–SE4): target 3,600 MW by 2045 — up from 2,800 MW today
These targets are in a prior government assignment report and are directional planning benchmarks, not binding commitments. (Source - Svk Planering för ökad elanvändning (2025))
LMA2026 welfare confirmation: Svk’s 2050 scenario analysis finds high total electricity-market benefit from +500 MW on the internal snitt. The benefit of reinforcing Snitt 1 rises over the analysis period — especially in the high-electrification HP/HF scenarios, driven by surging demand in northern Sweden — while the benefit of further Snitt 2 reinforcement falls relative to 2026, a direct consequence of the capacity already added by the NordSyd program. (Source - Svk LMA2026 Långsiktig Marknadsanalys, Long-Term Market Analysis)
Why it matters
The north-south bottleneck is the single most consequential constraint in the Swedish electricity system:
- It causes persistent price differences between northern and southern bidding areas
- It limits the ability to use northern hydropower and wind to serve southern demand
- It constrains new industrial connections in the north (green steel, hydrogen, data centers) by limiting how much generation can be exported south
- It creates Congestion Management needs that drive demand for Flexibility
NordSyd, combined with reinvestments that also increase capacity, aims to substantially increase intersection 2 and intersection 4 transfer capacity through the 2030s.
Timeline and investment
NordSyd projects are among the largest items in Svk’s SEK 225 billion investment plan. Individual components span from contracting phase (construction imminent) to under consideration (still being studied). The source’s Table 4 (“Projects with the largest investments 2025–2035”) lists Kustpaketet (SEK 17bn), Midskog–Malsjö (SEK 14bn), and Inlandspaketet (SEK 13bn) among its largest entries — but that table spans all investment motives (it also includes non-NordSyd projects like Stockholm at SEK 30bn), and the source never explicitly labels these three as NordSyd sub-packages. The geographic naming makes a NordSyd connection plausible but this specific cost breakdown is this wiki’s own inference, not a confirmed NordSyd-specific figure.
Upon full completion — “by the end of the 2030s” per the source (not stated as extending into the 2040s) — transmission capacity at intersection 2 increases from the current 7,300 MW to approximately 10,500 MW. (Source - Svk Network Development Plan 2026-2035)
Relationship to flexibility
NordSyd is the physical infrastructure solution to the north-south congestion problem. Flexibility is the operational and market-based complement:
- Until NordSyd is built: flexibility mechanisms (demand response, storage, conditional connections) are the primary tools for managing congestion within existing capacity
- After NordSyd: flexibility remains necessary for real-time balancing and managing remaining or new bottlenecks, but the structural congestion is reduced
- During construction: grid outages for construction can temporarily reduce available capacity, increasing the need for flexibility during the build-out period itself
The long lead times (10–15 years) for transmission projects like NordSyd fundamentally explain why Sweden cannot simply “build its way out” of grid constraints — flexibility is a necessary bridge.
DSO impact during construction
NordSyd construction creates a specific temporary problem for DSOs whose regional grids are connected to the affected transmission corridors. E.ON Energidistribution‘s DNDP explicitly identifies this: during 2027–2030, Svk’s NordSyd construction will cause E.ON’s Gävleborg and Västernorrland regional grids to be more heavily loaded than normal, as power flows reroute through alternative paths. This temporarily reduces the capacity available for new consumption connections in those counties.
When the NordSyd projects are completed (2032–2035), E.ON’s available capacity is expected to return to pre-construction levels — and then exceed them as NordSyd adds transfer capacity.
Practical implication for the 2027–2030 period: the capacity ratings (B/C) in Gävleborg and Västernorrland in E.ON’s DNDP are not caused by local network weaknesses but by the upstream stamnät construction. This is a temporary constraint with a defined resolution date. (Source - E.ON Nätutvecklingsplan 2025-2034)
Vattenfall’s NordSyd Västeråsbenet involvement: Vattenfall Eldistribution‘s DNDP includes Projekt 11 — Kapacitet Västmanland (NordSyd Västeråsbenet) as a major investment project — licence approved, commissioning 2025–2030. This is Vattenfall’s regionnät investment to accommodate the Västeråsbenet component of NordSyd, which passes through Vattenfall’s Mellan area in Västmanland. Vattenfall’s assessment: with the NordSyd Västeråsbenet project completed (from 2028), the Mellan area meets need. Before 2028, the area has limited spare capacity from the overlying stamnät. (Source - Vattenfall Eldistribution Nätutvecklingsplan 2025-2034)
Sources
Linked from 29
- Bidding Areas
- Capacity Adequacy & Flex
- Clean Energy Package
- Congestion Management
- DNDP First Round — DSO Profiles
- Electric Grid Structure
- Electric Power Transmission
- Ellevio
- Flexibility
- Grid-Forming Inverters
- LMA
- Nord Pool
- Source - CONDON Nordic Position on Grid-Forming (2025)
- Source - E.ON Nätutvecklingsplan 2025-2034
- Source - Electricity Market Regulation 2019/943
- Source - Ellevio Nätutvecklingsplan 2025-2034
- Source - Svk Kapacitetskarta 2026
- Source - Svk LMA2024 Långsiktig Marknadsanalys
- Source - Svk LMA2026 Långsiktig Marknadsanalys
- Source - Svk Network Development Plan 2026-2035
- Source - Svk Planering för ökad elanvändning (2025)
- Source - Svk Strategi mot 2030 (2026)
- Source - Svk Systemutvecklingsplan 2022-2031
- Source - Svk Utlandskablar Uppdrag Reviderad Investeringsplan (2026)
- Source - Svk Verksamhetsplan 2026-2028
- Svenska kraftnät
- Svk Grid Planning
- Swedish DSOs
- Vattenfall Eldistribution