Flexnavet › WikiWiki ›Energikontor Vast Smart Laddning Trollhattan (web)
Flexnavet
BläddraBrowse

Energikontor Vast Smart Laddning Trollhattan (web)

Source Updated 2026-09-22 Cited by 2 pages

Energikontor Väst (regional energy office, Trollhättan) web article, “Smart laddning minskar behovet av nätutbyggnad”. No author or publication date given on the page (published above is the fetch date) — a marketing/knowledge-base article, not a formal report, though it summarizes a real practical pilot. The fuller “Living Lab” experience report behind this article, Mätning och styrning av eleffekt i en del av Trollhättan, is ingested separately as Source - Mätning och Styrning Eleffekt Trollhättan Living Lab (2026).

Summary

Trollhättan Energi, Kraftstaden Fastigheter, and Innovatum Science Park ran a practical smart-load-control pilot in a mixed residential/industrial area of Trollhättan, focused specifically on EV charging as one of the fastest-growing local load categories. Consumption was measured at 10-second resolution via smart-meter HAN ports.

Findings:

  • Load control worked technically, but charging power should never be reduced all the way to zero — some vehicles interpret a full stop as the charging session ending, rather than a temporary pause.
  • Different car models behave differently when power resumes after a reduction.
  • Older chargers without open communication standards (APIs) cannot be remotely controlled at all — a hard technical floor, not a tuning problem — making open-standard requirements a critical procurement decision, not an afterthought.
  • Property owners can add charging points without new, expensive grid connection contracts; DSOs can defer or avoid transformer-station investment; end users see minimal disruption since charging still happens, just at adjusted power during peak periods.
  • Framed as primarily an organisational challenge, not a technical one: “tekniken finns och den fungerar” (the technology exists and works) — success depends on clear roles, cross-actor collaboration, and mandating open standards at procurement time.

Relevance to wiki topics

TopicRelevance
Grid Capacity UtilizationA concrete Swedish technical+organisational case for capacity release via smart EV-charging load control, avoiding transformer-station investment
OpenADRIndependent confirmation that open communication standards are a hard prerequisite for remote load control — older chargers without them are simply not controllable, not just harder to integrate
Vehicle-to-GridAdjacent technical finding relevant to any smart/managed charging deployment: never cut power to zero, since vehicle firmware can misinterpret it as session end