Flexnavet › WikiWiki ›Anslutningsplikt
Flexnavet
BläddraBrowse

Anslutningsplikt

Concept Updated 2026-10-06

A specific statutory obligation, not a general principle — grid companies must connect on request within a two-year presumptive maximum, a limit Ei's own supervisory review found routinely missed by years, not months.

The tools meant to relax this obligation without new wires — villkorade avtal, flexible connection agreements — are essentially unused at regional and transmission level, and four of the seven reviewed companies had no established method for evaluating them. The duty itself is well understood, but the flexible way of satisfying it barely exists in practice yet.

Presumptive maximum connection time — ~2 yearsSvk PM2026:05 — 60% of connections exceeded both the 2-year limit and the customer's own deadlineOffer times found (regional DSOs + Svk, 2023-24) — 406-1,620 days

The statutory connection obligation: a Swedish grid company’s legal duty to connect a customer’s facility to its network on request. Anslutningsplikt (also anslutningsskyldighet) is the baseline duty that conditional and flexible connection products modify. It is the legal reason a DSO — or even Svenska kraftnät at transmission level — cannot simply refuse a connection when the grid is congested (refusal is permitted only within the narrow limits of 4 kap. 2 §, below), and therefore a central driver of Congestion Management and Flexibility needs.

The obligation is grounded in the Swedish Electricity Act (ellagen, 1997:857; from 1 January 2027 the new Elmarknadslagen). Key provisions:

  • 4 kap. 1 § — the connecting grid company must, on request, connect a facility on objective, non-discriminatory and reasonable terms (Ei PM2026:05).
  • 4 kap. 2 § — refusal is allowed only if the grid lacks free capacity and the shortage cannot be remedied in a socioeconomically justified way without reinforcing the grid, or if there are other särskilda skäl (special reasons), which Ei reviews case by case. Ei reads this provision as also allowing a grid company (including Svenska kraftnät) to refer an application to a lower grid level for special reasons — e.g. where connection at the higher level would be inefficient or affect operational safety under 3 kap. 1 §. (Ei2025:05)
  • 4 kap. 3 § — a regional or transmission grid may connect a facility only if the local grid owner consents (or Ei grants permission); once the local grid has consented, the applicant may choose the regional or transmission level, and the regional grid’s consent is not required for a transmission application.
  • 4 kap. 5 § — connection must take place within reasonable time; it may exceed two years only if the connection’s scope and technical design make it necessary or there are other special reasons. (Ei PM2026:05)

A consequence of this hierarchy is that Svenska kraftnät’s transmission grid can become obligated to connect a customer who skipped the regional grid entirely. Ei recommends — but cannot require — that applicants apply at the lowest suitable voltage level and proceed upward (Ei2025:05). Connection prövning and concession assessment (nätkoncessionsprövning) are legally separate parallel processes. See Distribution System Operator › Connection process — Ei ställningstaganden and EU guidance.

The two-year presumptive maximum

Under 4 kap. 5 § ellagen roughly two years is the presumptive outer limit for a reasonable connection time; longer is allowed only where scope, technical design or other special reasons require it (and Ei expects such delays to be justified and transparent). In a congested grid this is increasingly unrealistic, and the gap between the legal presumption and operational reality is what Ei’s supervisory work has set out to measure.

Ei PM2026:05 reviewed how six regional DSOs and Svk fulfilled the obligation in 2023–2024: offer times of 406–1,620 days and completion times of 3–8+ years, with 60% of Svk’s connections exceeding both the two-year limit and the customer’s own deadline. The companion local-grid review is PM2025:01.

Relationship to conditional and flexible connections

Anslutningsplikt is the default — connection on firm, unconditional terms. The instruments that relax it are:

  • Villkorade Avtal (conditional connection agreements) — connection granted on the condition that the customer accepts curtailment under defined circumstances, deferring or avoiding reinforcement.
  • Flexible Connection Agreements — capacity-limited or time-limited connection, trading firmness for speed.

Ei’s PM2026:05 found these essentially unused at regional/transmission level: the rules are perceived as unclear and four of the seven companies had no established method to evaluate the costs and benefits of non-reinforcement alternatives (and several said their projects were too large for such solutions). This is a recurring theme — the connection obligation is firm and well understood, while the tools to satisfy it flexibly remain under-operationalised. The same dynamic underlies the luftbokning (speculative capacity reservation) and faktisk belastning doctrines analysed in Source - Ei R2024-14 Outnyttjad Kapacitet (2024).

Why it matters for flexibility

Because the grid company must connect on request, the binding question becomes how to honour the obligation when capacity is scarce. Flexibility — local markets, conditional connections, Dynamic Line Rating — is the means of meeting anslutningsplikt without (or before) building new wires. The strength of the obligation is precisely what makes flexibility a regulatory necessity rather than an optional efficiency.

A large-load illustration — Google at Torsboda

DN reported in September 2026 on a planned Google AI data centre in Timrå with a contractual build-out of up to 2 GW (Google’s Swedish office confirms discussions of up to 1 GW, in phases). E.ON, which as grid company cannot refuse the connection, is planning a new heavy line to the site, with applications due in the autumn. The case shows how far the obligation reaches: the connection must be offered even where it requires a new heavy line and a major rebuild, while the demand that such users co-finance new generation has no legal instrument behind it today, according to the finance-market minister quoted (Source - DN Googles Datacenter Torsboda Timrå (2026)).

Data gaps

  • Whether Ei will move from supervision to binding rule clarification on connection-time limits — PM2026:05 says Ei will continue its supervisory work and analyse whether rule clarifications or changes are needed, but sets no date
  • How the obligation is restated in the new Elmarknadslagen (in force 1 January 2027) versus the 1997 ellagen text
  • Volume of connections actually granted on conditional/flexible terms at regional/transmission level (PM2026:05 found the tools essentially unused — a baseline of ~0)

Sources

Närliggande sidorNearby pages 11

KonceptConcept EntitetEntity

Klicka på en nod för att gå dit. Dra för att panorera, rulla för att zooma. Click a node to go there. Drag to pan, scroll to zoom.