Flexnavet › WikiWiki ›EU Commission Draft Revised RfG and Annexes (2026)
Flexnavet
BläddraBrowse

EU Commission Draft Revised RfG and Annexes (2026)

Source Updated 2026-09-18 Cited by 4 pages

Type: Draft Commission Delegated Regulation + Annexes 1–3 (preliminary, not adopted) + Ei news coverage Reference: Ref. Ares(2026)6819642 (08/07/2026) Date: draft published for consultation July 2026; consultation closes 25 August 2026 Title: Commission Delegated Regulation (EU) …/… establishing a network code on requirements for grid connection of generators and repealing Regulation (EU) 2016/631

Summary

The European Commission has published its draft revision of RFG — the network code on grid-connection requirements for generators — for public consultation. This is the formal Commission draft implementing the amendments ACER recommended in December 2023 (“NC RfG 2.0”), closing the comitology-status data gap previously flagged in Generator Connection Requirements › Data gaps. The Commission states the technical requirements are based on ACER’s recommendation but that lessons from the April 2025 Iberian blackout were also incorporated. Upon adoption, RfG (EU) 2016/631 will be repealed and replaced by this new act. Ei is holding off finalising its own planned revision of EIFS 2018:2 while this EU-level process runs (see Source - EIFS 2018-2 Nätanslutning av generatorer and the note below).

Key content

Electricity storage modules (ESM) — new regulated category

The draft formally defines an “electricity storage module” (ESM): a power-generating module that can inject and consume active power for energy storage behind a single connection point, including V2G EV and V2G EVSE with bidirectional functionality, but excluding pump-storage. ESMs are subject to the same requirements as power-generating modules unless otherwise justified by their specific characteristics — the formal removal of RfG Art. 3.2(d)‘s storage exclusion that the wiki’s existing NC RfG 2.0 summary anticipated.

Grid-forming capability

Article 29 (“Grid forming capability”) requires the unit to behave, at its terminals, as a voltage source (rather than a current-follower) — including synthetic inertia where required. The mandate is two-tier, not a single uniform TSO discretion “from Type A/B upward”: for Type A power park modules and most Type B modules, grid-forming only becomes mandatory once the TSO (in coordination with DSOs) has submitted a national phase-in roadmap and the regulatory authority has set a date (Art. 29(1)–(2)); but large Type B modules — those connected at 110 kV or above, or ≥10 MW connected below 110 kV to a feeder/substation with transformation to 110 kV or above — are mandated directly by Article 30(3), with no TSO roadmap or regulatory-authority decision required, and Type C and D power park modules are mandated directly via Articles 31–32 (which cross-reference Art. 29(3)–(6) and Art. 30 unconditionally). This matches and gives regulatory teeth to the grid-forming direction already tracked in Source - Svk Driftsäkerhet Augusti 2025 and Source - CONDON Nordic Position on Grid-Forming (2025).

V2G electric vehicles and EVSE — mandatory technical requirements

V2G EV and V2G EVSE are formally defined and brought into scope (recitals 5 and 33; Article 2, definitions (64)–(67)). Application timeline once the Regulation enters into force:

  • 3 years for new vehicle types
  • 4 years for all new vehicles placed on the market
  • (For power-generating modules generally, 2 years unless otherwise specified — until then, RfG (EU) 2016/631’s existing requirements continue to apply.)

Annex III — Certification Framework for V2G EV and V2G EVSE (developed with industry stakeholders) establishes how conformity is demonstrated:

  • Functional split: the EV and EVSE (AC or DC) are certified individually, based on each component’s contribution to grid-code compliance
  • Conformity assessment test setups, configuration ranges, parameter sets, and acceptance criteria are based on EN 50549-10:2022, with V2G-specific adaptations
  • Certification is performed by certifiers accredited under EN ISO/IEC 17065 and recognised by the national EA (European co-operation for Accreditation) affiliate, per Regulation (EC) No 765/2008
  • EVSE-based compliance: the V2G EVSE manufacturer provides a country-specific compliance certificate
  • EV-based compliance: for AC V2G EVs, compliance is normally demonstrated through the Whole Vehicle Type Approval (WVTA) framework; before WVTA becomes effective for this purpose, manufacturers may seek certification directly under this Annex; a Union-wide certificate covers AC V2G EVs excluded from WVTA
  • Product families: certificates may extend to other products in the same family (±50% of rated power, same communication protocol/software, same grid-code-relevant control algorithm) without repeating tests — separate family definitions for AC V2G EV systems, DC V2G EVSE, and AC V2G EVSE

Annexes I and II (tables/figures) were not yet populated in this draft (“Tables and Figures to be moved here”).

RoCoF ride-through for storage

Electricity storage modules must withstand rate-of-change-of-frequency events: ±4.0 Hz/s (0.25 s) / ±2.0 Hz/s (0.5 s) / ±1.5 Hz/s (1 s) / ±1.25 Hz/s (2 s).

Swedish regulatory response

Per Ei’s own news coverage (EU-kommissionen har påbörjat revidering av RfG, 2026-07-09): Ei began its own revision of EIFS 2018:2 in 2025 and sent a remissförslag in February 2026 (coordination requirements between system operators on site-specific requirements, converting some national generally-applicable requirements into site-specific ones, and clearer cross-references to RfG articles). Because the Commission’s draft covers much of the same ground, Ei has decided not to proceed with the substantive EIFS 2018:2 changes at this stage — implementing them now risks either double regulatory change or having to re-open national rules once the new RfG is adopted. Ei will instead review EIFS 2018:2 for consequential updates (e.g. references to updated bemyndiganden, possibly a dispensation rule) once the EU-level revision is clearer, and is urging Swedish market actors to submit comments directly to the Commission’s consultation before 25 August 2026.

Relevance to wiki topics

TopicRelevance
Generator Connection RequirementsCloses the “EC comitology status of NC RfG 2.0” data gap; the NC RfG 2.0 section can now cite a concrete draft with application timelines
Source - EIFS 2018-2 Nätanslutning av generatorerEi’s planned amendments to this regulation are now paused pending the EU-level revision
Vehicle-to-GridFirst formal EU-level V2G technical requirements and certification framework
Source - ACER Recommendation 03-2023 NC RfG DC (2023)This draft is the Commission’s response to that recommendation
EiRegulatory response strategy (holding off national changes)