Nordic TSOs Grid Connection Requests Statement (2026)

Source Updated 2026-09-20 Cited by 2 pages

Joint Nordic TSO statement, Strong growth in grid connection requests challenges the power system (2026-06-23) — a coordinated communiqué from Fingrid, Energinet, Statnett and Svenska kraftnät on the surge in grid-connection requests and their shared response.

Key claims

  • Demand far exceeds capacity. Across all Nordic countries, connection requests now significantly exceed both existing and planned short-to-medium-term grid capacity — mirroring the rest of Europe (energy transition + new industrial demand).
  • Grid investment cannot solve it alone. Despite scaled-up investment, requested volumes exceed existing and planned capacity; making full use of the grid increasingly depends on efficient location of consumption/production and on increased flexibility to use existing capacity and enable higher connection volumes.
  • A few very large projects dominate requested capacity, so their realization (or not) decisively shapes system development and the room for other requests.
  • “First come, first served” has “in many cases already shifted” toward maturity-based assessments (not Nordic-wide, per the raw); further adjustment toward “more dynamic and flexible access models” is called for.
  • Country measures:
    • Denmark (Energinet) — maturity requirements, payments in early project phases, queue/capacity-allocation adjustments. Requested capacity is now ~8× today’s total peak load; some projects larger than the whole Copenhagen area. Calls for a political prioritization “compass” (possibly new regulation). (Thomas Egebo)
    • Finland (Fingrid) — broader toolbox: new connection-process principles, updated general connection terms, flexible connection agreements, and power-based tariffs. Explicitly: making FCAs a permanent tool would significantly enhance the ability to connect customers. (Asta Sihvonen-Punkka)
    • Norway (Statnett) — plans to implement strengthened maturity requirements for large consumption; ordinary/smaller projects prioritized; public connection-request list; the Stortinget amended the Energy Act to enable prioritization of connections for national-security interests. (Elisabeth Vike Vardheim)
    • Sweden (Svk) — structured stepwise connection process with maturity-based queue management; plans to launch a capacity-zones pilot in the coming year as a complement, to steer location/connection solutions toward available capacity. (Thomas Pålsson)
  • Shared responsibility: addressing this needs consumption and generation developed in conjunction, plus close cooperation with regulators/policymakers.