Flexnavet › WikiWiki ›Svk Strategisk Reserv Upphandling 2026-2027 (2026)
Flexnavet
BläddraBrowse

Svk Strategisk Reserv Upphandling 2026-2027 (2026)

Source Updated 2026-09-07 Cited by 1 page

Svenska kraftnät news notice opening the supplier-qualification stage for the strategisk reserv procurement covering winter 2026/2027 — the third procurement cycle under Lag 2025:50 / Förordning 2025:835.

Notice: “Upphandling av Strategisk reserv 2026/2027 inleds med leverantörskvalificering” (svk.se); exact publication date not stated in fetched content. The raw copy and URL in the frontmatter are the follow-up notice of 4 September 2026 (see Update below); the original notice has no raw copy.

Key findings

Contract period: 16 November 2026 – 15 March 2027.

Geographic scope: SE3 and SE4 only — unchanged from the first two procurement cycles.

Eligible resources: production facilities, energy storage installations, and demand-flexibility providers — unchanged technology-neutral eligibility.

Process stage: at time of publication, Svk had opened supplier qualification (leverantörskvalificering) via the e-Avrop procurement platform — qualification is a mandatory prerequisite to bid in the subsequent auction. Qualification applications close 15 May 2026.

Not yet published: target volume (MW) and price cap design for this cycle — the notice covers process/timeline only, not commercial parameters.

Timing note: the qualification deadline (15 May 2026) had already passed by the time this source was ingested (25 August 2026) — the procurement is very likely further along (qualification closed, auction possibly run or underway) than this notice’s own snapshot describes. A more current Svk notice should be checked before citing this page’s process-stage description as current.

Update (2026-09-07) — tender/bid-invitation phase opened

A follow-up Svk notice, “Upphandlingen av strategisk reserv går in i nästa fas” (published 4 September 2026), states Svk began the procurement by qualifying suppliers in April 2026, and confirms the process has advanced: supplier qualification (step 1) is complete, and the tender phase (step 2) has now opened — suppliers who qualified in step 1 are automatically invited via the e-Avrop procurement tool to submit bids. Contract period confirmed unchanged: 16 November 2026 – 15 March 2027. Legal basis restated: Förordning (2025:835) om en kapacitetsmekanism för elmarknaden, decided 21 August 2025. Target volume and price cap remain unpublished — this notice covers process stage only, same as the original.

Relevance to existing wiki topics

  • Strategisk Reserv — this is the source for the page’s “Third procurement” data gap; confirms contract period and current process stage but does not yet answer target volume, price cap, or result — gap should remain open, narrowed to those three unknowns.
  • Capacity Adequacy and Flexibility as the Missing Reserve — the ongoing procurement cadence is directly relevant to Sweden’s LOLE trajectory and capacity-adequacy planning.