Ei Anslutningsavgift 2026 Schablonvärden (2025)

Source Updated 2026-09-22 Cited by 2 pages

Ei’s methodology memo PM2013:03, version 12 (updated 2025-11-28), setting the maximum reasonable connection fee (skälig anslutningsavgift) for 16–25 A (fuse size) connections, plus the accompanying news notice of 3 December 2025 announcing the 2026 update (Raw/Clippings/Anslutning till elnätet 2026 - här är de avgifter som Ei anser skäliga.md, fetched verbatim 2026-09-22; the notice says the new values apply from 1 January 2026, to connections whose quotes are written from that date). This is the current schablon regime — distinct from and pre-dating EIFS 2026:10, the binding nationwide connection-fee föreskrift entering force 1 January 2027 (see Source - EIFS 2026-10 Anslutningsavgifter för Elektriska Anläggningar (2026)).

Legal basis: 4 kap. ellagen (1997:857) — §1 (connection duty), §2 (capacity-shortage exception), §10 (fee must cover the grid company’s reasonable costs), §13 (2-year dispute deadline)

Applies to: connection offers written from 1 January 2026 onward; distances 0–1,800 m fågelvägen (as the crow flies) from the connection point

Key findings

2026 fee schedule (excl. VAT):

Distance to nearest connection point (fågelvägen)Fee
0–200 m43,000 kr flat
200–600 m43,000 kr + 369 kr/m
600–1,200 m190,600 kr + 953 kr/m
1,200–1,800 m762,400 kr + 562 kr/m
>1,800 mindividual assessment (no schablon); 1,099,600 kr (the fee at 1,800 m) is used as always reasonable for such connections, provided no other customers can be expected to connect to the same extension

Each tier’s base is the maximum fee at the end of the previous tier — a cascading schablon, not four independent bands.

Cost basis: the 0–200 m and 200–600 m figures derive from a 2009 Statistics Sweden (SCB) survey of actual DSO connection costs 2006–2008, plus a 2008 Ei review of 189 pending cases (used to derive a 0.815 fågelvägen-to-actual-distance conversion factor, 95% CI ±0.017). The 600–1,200 m and 1,200–1,800 m figures derive from the EBR cost catalogue (industry-standard planning/costing tool, EBR 2025 edition) — specifically högspänningsledning (562 kr/m), nätstation (132,989 kr), and transformator (101,563 kr) cost codes, with nätstation+transformator costs allocated only within the 600–1,200 m band since Ei treats those as fully covered by that point.

Indexation: figures are re-based annually via the EBR cost index (rebased to a 2013 base year as of the 2023 update; 2022→2025 index moved 149→180). Historical progression (grundavgift / 200–600m meter-fee / 600–1200m meter-fee / 1200–1800m meter-fee):

YearBase (0–200m)200–600m/m600–1200m/m1200–1800m/m
Original (2007 prices)22,100 kr189 kr404 kr240 kr
202230,500 kr262 kr640 kr389 kr
202440,000 kr342 kr810 kr475 kr
202543,300 kr371 kr901 kr504 kr
202643,000 kr369 kr953 kr562 kr

Note 2026’s base fee (43,000 kr) is slightly lower than 2025’s (43,300 kr) despite the 600–1,200m and 1,200–1,800m meter-fees rising. The PM does not explain this; it recalculates the SCB-derived bands from a 2022 origin year (35,624 kr × 180/149 = 43,036, rounded to 43,000 kr; 305 kr/m × 180/149 = 368.5, rounded to 369 kr/m).

Legal function: this is a ceiling-testing tool, not a price control — DSOs set their own fees and aren’t required to use Ei’s method. A customer can request Ei review a fee as a dispute under 4 kap. 1§ ellagen; Ei doesn’t challenge a fee that stays at or below the schablon’s computed maximum. The PM notes Kammarrätten approval of using schablon amounts and of EBR as a suitable tool, and its version history records that Förvaltningsrätten (Linköping) rulings led Ei in 2017 to adjust the meter-based fees over 600 m (v3, disallowed EBR deductions) and to remove the general “delningsprinciper” (cost-sharing-across-future-customers assumptions, v4); sharing is now assessed case by case where further customers can reasonably be expected.