Svk Ansökningskö Statistik (2026-09)
Source details
- Type
- Dataset
- Publisher
- Svenska kraftnät
- Published
- 2026-09-02
- Links
- svk.se/aktorsportalen/anslut-till-transmissionsnatet/information-om-pasvk.se/aktorsportalen/anslut-till-transmissionsnatet/information-om-pasvk.se/aktorsportalen/anslut-till-transmissionsnatet/information-om-pa
A dated snapshot of Svenska kraftnät‘s connection-queue statistics for the transmission grid (stamnätet), per 1 September 2026 (pages reviewed 2 September 2026). The pages carry dated snapshots that are presumably replaced when Svk updates them, so the figures here are quoted as “per 1 september 2026”; the page text fetched on 6 Oct 2026 still showed this snapshot. Offshore wind is outside the statistics because it is handled in a separate process.
Definition (Svk): “applied power” is the total power in Svk’s connection queue, that is until capacity has been reserved and a preliminary decision (förhandsbesked) sent.
Applied power by connection type, whole country
| Connection type | Production | Consumption |
|---|---|---|
| Solar | 4,844 MW | |
| Onshore wind | 9,004 MW | |
| Other production | 4,348 MW | |
| Energy storage | 2,260 MW | 2,206 MW |
| Data centres | 6,984 MW | |
| Industry | 11,122 MW | |
| Other consumption | 5,630 MW | |
| Total | 20,456 MW | 25,992 MW |
Of the total applied power (excluding offshore wind), “utredning pågår” is 15,563 MW and “undersökning ej startad” is 30,885 MW.
By price zone, consumption (data centres in brackets)
| Zone | Consumption | Data centres | Production |
|---|---|---|---|
| SE1 | 11,537 MW | 495 MW | 4,320 MW |
| SE2 | 4,508 MW | 1,320 MW | 4,768 MW |
| SE3 | 9,293 MW | 5,169 MW | 9,983 MW |
| SE4 | 654 MW | none | 1,411 MW |
The consumption zone figures add up to the national 25,992 MW and 6,984 MW. The production zone figures add up to 20,482 MW against 20,456 MW nationally, a 26 MW difference that Svk’s pages do not explain (by type, solar differs by 36 MW and onshore wind by 10 MW). SE2 “other consumption” is printed as “565” without a unit.
Reserved capacity (förhandsbesked) per year
| Year | Production, MW | Consumption, MW |
|---|---|---|
| 2026 (to August) | 3,009 | 780 |
| 2025 | 1,170 | 3,695 |
| 2024 | 1,142 | 1,923 |
| 2023 | 3,045 | 715 |
| 2022 | 1,100 | 3,532 |
| 2021 | 1,219 | 241 |
| 2020 | 488 | 1,050 |
Svk explains that capacity is reserved when applicants receive a förhandsbesked, which removes the corresponding power from the queue; actual allocation comes later, at the connection agreement. The figures are maximum power and say nothing about simultaneous use, and Svk compares them with Sweden’s peak-load hour of “about 25,000 MW”. The queue consumption figure of 25,992 MW and Svk’s peak-load figure are different quantities and should not be mixed.
Not captured: the pages’ charts (assigned, reserved and applied power overview, updated 18 Aug 2026, and desired and planned commissioning dates) and the per-zone PDFs were not read.
Relevance to existing wiki topics
- Svk Transmission Grid Planning — the queue behind the anvisningssystem reform; data centres are just over a quarter of queued consumption (6,984 of 25,992 MW) and SE3 holds most of them
- Anvisningssystem — the geography of the queue against the kapacitetszoner logic
- Source - Svk Kapacitetskarta 2026 — the capacity map, which shows available capacity by county